Contract No. HY/2012/06
Widening of Fanling Highway – Tai Hang to Wo Hop Shek Interchange

Mar 2018
Piling Works of the Proposed Noise Barriers along Fanling Highway northbound

Piling Works of the Proposed Noise Barriers along Fanling Highway northbound

Excavation for Construction of Proposed Retaining Wall between Fanling Highway southbound and Realigned Jockey Club Road

Excavation for Construction of Proposed Retaining Wall between Fanling Highway southbound and Realigned Jockey Club Road

Construction for Proposed Wo Hop Shek Pedestrian and Cycle Bridge.

Construction for Proposed Wo Hop Shek Pedestrian and Cycle Bridge.

Construction of Proposed Noise Barriers along Fanling Highway northbound near Tai Hang

Construction of Proposed Noise Barriers along Fanling Highway northbound near Tai Hang

Commissioning of Tempoary Tai Wo Footbridge on 20 Mar 2018

Commissioning of Tempoary Tai Wo Footbridge on 20 Mar 2018

Construction of Road Works along the Widened Fanling Highway southbound

Construction of Road Works along the Widened Fanling Highway southbound